Timeline
Our overall timeline for the project is:
- 2003-2006, Land acquisition, funded by Pro-Parks Levy
- 2006, Initial design, completed by Barker Landscape Architects
- 2007, Fundraising
- 2008 (Spring), Construction
- 2008 (Fall), Park opens
See below for our detailed plans for 2007.
Winter ’07
- Community Brochure Mailout
- 2007 Community Meeting and Fundraising Kickoff
- Design at 50%
- GOAL: direct donations at $1,500
Spring ’07
- Apply for Large Project Fund ($100,000)
- GOAL: 50% funding
- GOAL: direct donations at $4,000
Summer ’07
- GOAL: 80% funding
- GOAL: direct donations at $7,000
Fall ’07
- Construction Drawings Complete
- GOAL: 95% funding
- GOAL: direct donations complete at $10,000
- Apply for Large Project Fund ($100,000)
- GOAL: 50% funding
- GOAL: direct donations at $4,000
Summer ’07
- GOAL: 80% funding
- GOAL: direct donations at $7,000
Fall ’07
- Construction Drawings Complete
- GOAL: 95% funding
- GOAL: direct donations complete at $10,000
- Construction Drawings Complete
- GOAL: 95% funding
- GOAL: direct donations complete at $10,000